Mumbai-Ahmedabad Bullet Train project hits milestone with MT-5 tunnel breakthrough
Updated On: 02 January, 2026 01:54 PM IST | Palghar | mid-day online correspondent
The tunnel excavation, carried out from both ends over 18 months, employed a cutting-edge drill-and-blast method, allowing real-time monitoring of ground behaviour and enabling the installation of support systems such as shotcrete, rock bolts, and lattice girders based on site conditions

MT-5 is part of the seven mountain tunnels in Maharashtra. PIC/ SCREENGRAB FROM X
The Mumbai-Ahmedabad Bullet Train project marked a major milestone with the breakthrough of the MT-5 mountain tunnel, the second tunnel completed in the state for the high-speed rail corridor. Spanning 1,480 meters (~1.5 km), the tunnel connects key points between Virar and Boisar in Palghar district.
The tunnel excavation, carried out from both ends over 18 months, employed a cutting-edge drill-and-blast method, allowing real-time monitoring of ground behaviour and enabling the installation of support systems such as shotcrete, rock bolts, and lattice girders based on site conditions.