Stop all new road digging and ensure concreting work is completed by May 1: Civic chief orders

Move comes after BMC started getting continuous complaints about roads dug up across the city. After getting continuous complaints about dug-up roads, last week Gagrani held a meeting with senior officials. At this meeting, Gagrani also directed officials to visit road concreting sites regularly

Listen to this article :
Road concreting work going on at Wadala. Pic/Atul Kamble

Road concreting work going on at Wadala. Pic/Atul Kamble

BMC Commissioner Bhushan Gagrani has ordered the road department as well as all ward offices to not undertake any new road digging work that cannot be completed by May-end. Currently, 433 km of roads with 1,173 patches across the city are being concreted. After getting continuous complaints about dug-up roads, last week Gagrani held a meeting with senior officials. At this meeting, Gagrani also directed officials to visit road concreting sites regularly. 

On Tuesday, Deputy Municipal Commissioner of Infrastructure sent out an internal order stating, “It has been directed that no new road shall be excavated for concreting and it is strictly instructed that all such road work and allied work shall be completed on or before May 31,2025 to prevent inconvenience to commuters and the public in large”. BMC officials claim that they will complete road concreting work by May end. 

How do you like the new new mid-day.com experience? Share your feedback and help us improve.

Read Next Story
Mumbai Diary: Thursday Dossier

Trending Stories

Latest Photoscta-pos

Latest VideosView All

Latest Web StoriesView All

Mid-Day FastView All

Advertisement