Mumbai Metro 7A may lose Rs 250 crore if Airport Colony ramp and viaduct face demolition

The problem is linked to height restrictions imposed by the Airports Authority of India (AAI), as the Metro structure falls within the air funnel zone of Chhatrapati Shivaji Maharaj International Airport (CSMIA)

  • WhatsAppBookmarkBookmark
Listen to this article :
The 3.42-km Metro 7A corridor will connect Terminal 2 of CSMIA with the wider Metro network, providing connectivity towards Mira-Bhayandar and South Mumbai through the underground Aqua Line. File Photo

The 3.42-km Metro 7A corridor will connect Terminal 2 of CSMIA with the wider Metro network, providing connectivity towards Mira-Bhayandar and South Mumbai through the underground Aqua Line. File Photo

The Mumbai Metropolitan Region Development Authority (MMRDA), which is constructing the Metro 7A corridor, could face a potential loss of around Rs 250 crore due to issues related to the design and construction of the Airport Colony station ramp and viaduct.

The problem is linked to height restrictions imposed by the Airports Authority of India (AAI), as the Metro structure falls within the air funnel zone of Chhatrapati Shivaji Maharaj International Airport (CSMIA).

Read Next Story
MPSC exam paper leak: Three officials among six arrested by Mumbai Crime Branch›

Trending Stories

Latest Photoscta-pos

Latest VideosView All

Latest Web StoriesView All

Mid-Day FastView All