Home / Mumbai / Mumbai News / Article / Mumbai JVPD flyover: BMC eyes December 2027 completion, ahead of March 2028 deadline

Mumbai JVPD flyover: BMC eyes December 2027 completion, ahead of March 2028 deadline

The BMC aims to complete Mumbai’s 1.75-km JVPD flyover by December 31, 2027, ahead of the scheduled March 2028 deadline. The project is expected to bypass five major traffic junctions and reduce peak-hour travel time from 45 minutes to around 20 minutes

  • WhatsAppBookmarkBookmark
Listen to this article :
The 1.75-km-long flyover, which will be 15.10 metres wide, is being constructed from the end of the CD Barfiwala flyover in Andheri West to the Juhu-Versova Link Road. PIC/BY SPECIAL ARRANGEMENT

The 1.75-km-long flyover, which will be 15.10 metres wide, is being constructed from the end of the CD Barfiwala flyover in Andheri West to the Juhu-Versova Link Road. PIC/BY SPECIAL ARRANGEMENT

The Brihanmumbai Municipal Corporation (BMC) aims to complete the Juhu-Vile Parle Development Scheme (JVPD) flyover by December 31, 2027, to ease traffic congestion in Mumbai’s western suburbs and improve road connectivity, the civic body stated in a press release issued on Wednesday.

Additional Municipal Commissioner (Projects) Abhijit Bangar reviewed the progress of the project, traffic management measures and construction timelines during an inspection. He directed officials to expedite the work and open the flyover to traffic by December 31, 2027, ahead of the scheduled deadline of March 31, 2028.

Read Next Story
'Drought of transparency': MNS uses cartoon to protest alleged voter list errors›

Trending Stories

Latest Photoscta-pos

Latest VideosView All

Latest Web StoriesView All

Mid-Day FastView All