Mumbai: MahaRERA rejects builder’s bid to dismiss 17 buyer complaints in landmark Jogeshwari project dispute
Updated On: 28 June, 2026 10:11 PM IST | Mumbai | Vinod Kumar Menon
MahaRERA has rejected Jangid Homes Pvt Ltd's application to dismiss 17 complaints filed by purchasers of units in the delayed Jangid Annexe project in Jogeshwari East, holding the complaints to be prima facie maintainable

The Jangid Annexe project is located at Jogeshwari East in Mumbai. PIC/ADVOCATE ANIL Dsouza
In a significant order that could have far-reaching implications for buyer protection under the Real Estate (Regulation and Development) Act (RERA), the Maharashtra Real Estate Regulatory Authority (MahaRERA) has rejected an attempt by Jangid Homes Pvt Ltd to dismiss 17 complaints filed by purchasers of units in the long-delayed Jangid Annexe project at Jogeshwari East.
The promoter had argued that the units in question were industrial units and therefore outside the jurisdiction of MahaRERA. However, MahaRERA Member-II Ravindra Deshpande ruled that the complaints are prima facie maintainable, observing that the builder had repeatedly represented the project and the units as commercial in nature before purchasers as well as before MahaRERA itself.