Home / Mumbai / Mumbai News / Article / Mumbai: MahaRERA rejects builder’s bid to dismiss 17 buyer complaints in landmark Jogeshwari project dispute

Mumbai: MahaRERA rejects builder’s bid to dismiss 17 buyer complaints in landmark Jogeshwari project dispute

MahaRERA has rejected Jangid Homes Pvt Ltd's application to dismiss 17 complaints filed by purchasers of units in the delayed Jangid Annexe project in Jogeshwari East, holding the complaints to be prima facie maintainable

  • WhatsAppBookmarkBookmark
Listen to this article :
The Jangid Annexe project is located at Jogeshwari East in Mumbai. PIC/ADVOCATE ANIL Dsouza

The Jangid Annexe project is located at Jogeshwari East in Mumbai. PIC/ADVOCATE ANIL Dsouza

In a significant order that could have far-reaching implications for buyer protection under the Real Estate (Regulation and Development) Act (RERA), the Maharashtra Real Estate Regulatory Authority (MahaRERA) has rejected an attempt by Jangid Homes Pvt Ltd to dismiss 17 complaints filed by purchasers of units in the long-delayed Jangid Annexe project at Jogeshwari East.

The promoter had argued that the units in question were industrial units and therefore outside the jurisdiction of MahaRERA. However, MahaRERA Member-II Ravindra Deshpande ruled that the complaints are prima facie maintainable, observing that the builder had repeatedly represented the project and the units as commercial in nature before purchasers as well as before MahaRERA itself.

Read Next Story
'Mr PM, Mr CM, please help us save our ground': Mumbai football fraternity protests BMC's convention centre plan

Trending Stories

Latest Photoscta-pos

Latest VideosView All

Latest Web StoriesView All

Mid-Day FastView All