Andheri: BMC confident of completing Gokhale Bridge work by April deadline

Officials looking to complete approach road work by mid-February to finish project on time

Listen to this article :
Several deadlines set for the Gokhale bridge work have lapsed. Pics/Nimesh Dave

Several deadlines set for the Gokhale bridge work have lapsed. Pics/Nimesh Dave

The BMC still has a chance to meet the deadline to complete the Gopal Krishna Gokhale Bridge work. If the civic body manages to complete the last pier on both approaches by mid-February then the project work can be completed by April-end. According to a BMC official, lowering of the girder over the railway portion has been completed. The final work of installing a pier on approach roads on both sides is pending. “If we complete this task by mid-February, we can complete work by the end of April 2025. We are hoping the task will be completed in time,” the official told mid-day.

Only work of installing the last pier on both approach roads remains
Only work of installing the last pier on both approach roads remains

How do you like the new new mid-day.com experience? Share your feedback and help us improve.

Read Next Story
Horoscope today, January 7: Check astrological predictions for all zodiac signs

Trending Stories

Latest Photoscta-pos

Latest VideosView All

Latest Web StoriesView All

Mid-Day FastView All

Advertisement